Brew Mill Installation


Find the assembly instructions HERE !

Find the motor starter wiring information HERE !


Installing a machine on a stand:

If the machine is installed on a stand it is critical that this stand is built to handle the overall weight of the machine and product that will be in the machine. As a general rule of thumb the stand should be built will a 1.5 to 1 safety factor.

It is recommended to anchor the brew mill stand using Grade 5, 1/2" concrete anchors at a minimum thread length of 1". Anchor depth may vary based on application. Anchors should be torqued to approximately 40 ft. lbs.

An example of brew mill stand anchor locations is shown below:

Brew Mill Stand Anchor Locations

Bolting machine to the ground:

Concrete anchor bolts must be used when the machine is being installed on concrete. If the machine is being installed on a steel platform grade 5 bolts or better should be used. Machines should be checked for level, no matter where they are installed, before being secured.

It is recommended to anchor the brew mill stand using Grade 5, 1/2" concrete anchors at a minimum thread length of 1". Anchor depth may vary based on application. Anchors should be torqued to approximately 40 ft. lbs.

An example of brew mill anchor locations is shown below:

Brew Mill Anchor Locations

To prevent dust leaks:

 After the machine is in place and bolted, the seams between each flange should be sealed with silicone caulk, to ensure it stays dust tight.

Clearances around the machine:

It is important to take into consideration the space that is required for roll changes and routine maintenance work when deciding where to place your machine. Call RMS for recommended clearances.

Brew Installation Dimensions